How Many Concrete Blocks Do You Need for a Wall?
A standard 8x8x16 concrete block covers 0.889 square feet, so you need 1.125 blocks per square foot of wall. A 24x8 foot wall (192 sq ft) takes 216 blocks, or 227 with 5 percent extra. Subtract the area of doors and windows first, and add waste for cuts and breakage.
The rule: 1.125 blocks per square foot
A standard concrete block is sold as an 8 x 8 x 16 inch unit, but that is its nominal size. The block itself measures 7 5/8 x 7 5/8 x 15 5/8 inches, and the missing 3/8 inch is the mortar joint, so a laid block takes up exactly 8 x 16 inches of wall face. Archtoolbox describes nominal size as the actual dimension plus the width of the mortar joint, and CMHA's layout sheet (TEK 05-12) builds its wall layouts on the same nominal 8 by 16 inch unit and a 3/8 inch joint.
One block therefore covers 128 square inches, which is 0.889 square feet, and it takes 1.125 blocks to cover a square foot of wall.
order = blocks x (1 + waste %)
Everything else in this guide is that formula applied to real walls.
Blocks for common wall sizes
These counts are for standard 8 x 8 x 16 blocks, no openings and no waste. They match the concrete block calculator with the waste set to zero.
| Wall (length x height) | Area | Courses | Blocks |
|---|---|---|---|
| 20 x 4 ft | 80 sq ft | 6 | 90 |
| 20 x 6 ft | 120 sq ft | 9 | 135 |
| 30 x 6 ft | 180 sq ft | 9 | 203 |
| 40 x 8 ft | 320 sq ft | 12 | 360 |
A course is one horizontal row. Each course is 8 inches tall, so a wall's height in inches divided by 8 gives the number of courses, and the wall's length in inches divided by 16 gives the blocks in each row. The 30 foot wall comes out at 202.5 blocks and is rounded up to 203, because you cannot buy half a block.
Worked example: a 24 x 8 foot wall
Take a wall 24 feet long and 8 feet tall. The area is 192 square feet, and 192 x 1.125 gives 216 blocks. Counting it the other way gives the same answer: 24 feet is 18 blocks per course, and 8 feet is 12 courses, and 18 x 12 is 216.
Now add a waste allowance. At 5 percent, which is the calculator's default, the order becomes 227 blocks. At 10 percent it is 238. A few blocks always crack in transport or get cut in the wrong place, and a corner, a window or a door makes more cuts.
Subtract the openings
Doors and windows are holes in the wall, so take their area off before you multiply. A standard 3 x 7 foot door is 21 square feet. Subtract it from the 24 x 8 foot wall and the net area is 171 square feet, which is 193 blocks before waste and 202 blocks with 5 percent extra. That is 25 fewer blocks than the solid wall, and it is why measuring openings pays for itself on a long wall.
Do not subtract openings you plan to fill in with blocks later, and measure each opening at its finished size.
Other block sizes
Not every wall uses the 8 x 16 face. The same 24 x 8 foot wall, with 5 percent extra, takes very different counts depending on the unit:
- 8 x 16 inch face (standard): 227 blocks.
- 12 x 8 inch face: 303 blocks, 1.5 per square foot.
- 24 x 8 inch face (large): 152 blocks, 0.75 per square foot.
- 16 x 4 inch face (half-height): 454 blocks, 2.25 per square foot.
CMHA's TEK 02-02B notes that standard units are 8 inches high and 16 inches long, with widths from 4 to 12 inches, and that a wall built from half-high units is laid on a 4 inch vertical module instead of an 8 inch one. A half-height block doubles the number of courses, so a wall costs more in labor as well as in blocks.
Design the wall to the block
CMHA's TEK 02-02B recommends sizing wall height and opening heights to a multiple of the unit height, and laying out the length to fit the unit length. A wall that is 8 feet tall (12 courses of 8 inches) needs no cut blocks on the top row, while a wall 7 feet 10 inches tall does. Nudging a wall by a few inches to match the 8 inch module saves cuts, waste and time. The TEK 05-12 sheet covers the layout in detail, including allowances for framing around doors and windows.
Common mistakes
- Using the actual size instead of the nominal one. A 7 5/8 x 15 5/8 inch block is laid with a joint, so the wall math uses 8 x 16.
- Forgetting the waste. The exact count is a minimum. Always add something.
- Not subtracting openings. That overbuys, and it is the cheapest mistake to avoid.
- Counting the footing's blocks as wall blocks. A block foundation or stem wall below grade counts as its own wall, so measure the total height.
- Mixing up pallets and pieces. Suppliers sell blocks by the pallet, and the number per pallet varies, so ask for the count on the pallet you are buying.
What else to order
The block count is only the wall's units. The concrete block calculator does not count mortar, grout or reinforcing steel, because those depend on the wall design. Ask your supplier for mortar and grout amounts for your wall, and use the rebar calculator if the plans call for vertical or horizontal steel. A freestanding, tall, load-bearing or retaining wall is structural work, so check your local code and the plans before you build.
Calculators for this guide
Frequently asked questions
How many concrete blocks are in a square foot?
A standard 8x8x16 inch block, laid with a 3/8 inch joint, covers 8 x 16 inches of wall face. That is 0.889 square feet, so it takes 1.125 blocks to cover one square foot of wall.
How many concrete blocks do I need for a 20x6 foot wall?
A 20 by 6 foot wall is 120 square feet. At 1.125 blocks per square foot that is 135 blocks, with 9 courses of 15 blocks each. Add 5 percent for waste and you would order about 142.
How much extra should I order?
The block calculator defaults to 5 percent. Use 10 percent if the wall has several corners, a lot of openings, or you are cutting blocks for the first time. The extra covers cuts and breakage, and it is cheaper than a second delivery.
Sources and further reading
- Modular Layout of Concrete Masonry (TEK 05-12) — Concrete Masonry & Hardscapes Association
- Considerations for Using Specialty Concrete Masonry Units (TEK 02-02B) — Concrete Masonry & Hardscapes Association
- CMU Sizes, Shapes & Finishes — Archtoolbox
More guides
Estimates only. Always confirm quantities with your supplier or a qualified contractor before ordering, and add extra for waste and site conditions.